Bess for Grid Reinforcement for Ev Fast Charging Infrastructure
Challenge: Heinsberg saw the construction of one of the first high-performance fast-charging infrastructures for electric vehicles in Germany. However, the local power supply was unable to reliably handle the peak load of 180 kW. Without additional support, charging interruptions, frustration for EV drivers, and potential grid instability were all likely.
Our Solution: Lindemann-Regner stepped in as the technical partner: A customized battery energy storage system (BESS) was installed, combining HyperStrong batteries with our highly efficient power conversion system. Intelligent controls and fast response times enable the system to provide energy immediately during peak loads – the so-called “grid boosting”.
Project Progress: During commissioning, our team closely monitored each charging phase, adjusted the parameters for maximum efficiency, and ensured seamless integration into the existing network.
Result
The project has significantly improved grid stability and optimized charging performance for the EV charger. Key achievements at a glance:
- Stable charging power for the 180kW Hypercharger
- Avoiding expensive network upgrades
- Scalable solution for future fast charging infrastructure
- Customer satisfaction and network stability at the highest level
Technical Highlights
The technology used forms the backbone of the project and ensures high efficiency and safety:
- HyperStrong batteries + Lindemann-Regner inverter technology
- Peak shaving and grid boosting functionality
- TÜV-certified, high safety standards

Quantified Effects
Measurable results demonstrate the actual benefits of the system.
100%
Reduction of network overloads during all peak load cycles.
99,9 %
Ensuring stable and continuous system availability.
+8 %
Increasing charging efficiency for the 180kW EV charger.
-12t/year
Saving CO₂ emissions through intelligent load management.